Without a dike built by the Tennessee Valley Authority, part of Dandridge would have gone under the waters of Douglas Lake. The top of the dike reaches 1009 feet in elevation, seven feet higher than the crest gates of the dam. Below the reservoir's maximum water level would have been the Jefferson County Courthouse, the entire business district, the county jail, and about 1000 feet of Highway 92. Dandridge was where opposition to Douglas Dam centered, because more than 60,000 acres of fertile farmland would be lost. The Douglas Reservoir was critical in supplying the power Oak Ridge's Manhattan Project needed. Work on the Douglas Project began in 1942 and was finished in 382 days so that it could capture the winter rains of 1943 and generate the hydroelectric power that was needed.
Source: Tennessee Historical Commission marker 1C 90 (reworded by TennRoam)